The wind farm site is remote and presents a significant logistics challenge. Wind turbines and their propeller blades are large pieces of equipment that need special handling. LTWP commissioned Mammoet to conduct a route survey in Kenya to assess the state of the existing infrastructure and to determine the investments required to transport the turbines, equipment and materials to the site.
The study determined that some 200 km of road needed to be upgraded, and several bridges strengthened in order to transport the wind turbines to the site from the port in Mombasa. These costs are included in the financial model.